ROTARY SPLASH PAD
CONSTRUCTION
'North Bay's Family of Rotary' - the Rotary Clubs of North Bay and North Bay-Nipissing, worked closely with City of North staff over the past several years. Phase I was completed in time for the Splash Pad to open on August 30, 2019, just in time for the Labour Day Weekend.
June 28
|
July 3
|
July 4
|
July 15 - Washroom/Changeroom base
|
July 16 - Starting to take shape
|
July 17 - Pad is excavated and ready for granular base
|
July 17 - Two important members of the construction team - Megan Rochefort - City of North Bay Engineering Department and Daryl Farelli with Bruman Construction.
|
July 24 - Water line ready to be connected to municipal supply.
|
July 25 - Burying the water supply pipe.
|
August 22 - Sod laying.
|
August 26 - Concrete pad installation
|
August 26 - Concrete pad finished
|
PHASE II
Installation of sun shelters, benches, tables, washroom/changeroom mural and trees are underway and expected to be completed by earlier October 2020.
Installation of sun shelters, benches, tables, washroom/changeroom mural and trees are underway and expected to be completed by earlier October 2020.